Planning |
|
---|---|
OCID: | ocds-zinqhl-Kf8GMBiR |
Project Title: | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Procuring Entity: | MINISTRY OF PROJECT MONITORING AND EVALUATION |
Planning Rationale: | selective procurement method |
Budget ID: | Kf8GMBiR003388 |
Budget Description: | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Budget Amount: | ₦3,000,000,000 |
Budget Year: | 2019 Budgetary provision |
Procurement Method: | selective |
Procurement Category: | works |
S/N | Company | Envelope | Bid Opening Status | Tender Amount | Financial Bid Score % | E.O Award Status |
---|---|---|---|---|---|---|
1 | Klyn Construction Ltd | Price BOQ | Opened | 4186532350 | -1.4809389576728E-8 | Awarded |
AWARD |
|
---|---|
Award Title: | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Award Description : | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Award ID : | Kf8GMBiRi/Kf8GMBiR003392 |
Award Status : | active |
Award Date: | 2019-09-02T13:00 |
Award Criteria : | price Only |
Award Amount : | ₦4,186,532,350.62 |
Award Items Classification Scheme : | UNSPSC |
Award Items Classification ID : | 112893 |
Award Items Quantity: | 1 |
Award Items Unit : | unit |
Award Items Delivery Address : | Abakaliki Ebonyi State |
Contract Period Start Date : | 2019-09-02T07:43 |
Contract Period End Date : | 2020-09-02T22:00 |
Contract Period Duration in Days : | 367 |
Contractor/Supplier Name : | Klyn Construction Ltd |
Contractor/Supplier Address : | No 14 Onwe Road Abakaliki |
Contractor/Supplier Email : | klyn@gmail.com |
Contractor/Supplier Phone : | 08036680066 |
Contractor/Supplier website : | https://ebonyieprocure.eb.gov.ng/report/economic_operator.php |
Procuring Entity Name: | MINISTRY OF PROJECT MONITORING AND EVALUATION |
Procuring Entity Address : | ABAKALIKI, EBONYI STATE |
Procuring Entity Representative Email.: | monitoring@ebonyieprocure.eb.gov.ng |
Procuring Entity Representative Phone : | |
Procuring Entity website : | http://www.ebonyibudget.com/ |
Contract |
|
---|---|
Contract Title : | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Contract Description: | Approval for the revised contract sum due to some additional works on the construction of shopping mall Abakaliki |
Contract Award ID : | Kf8GMBiR |
Contract Status : | active |
Contract Period Start Date : | 2019-09-02T07:43 |
Contract Period End Date : | 2020-09-02T22:00 |
Contract Period Duration in Days : | 367 |
Contract Amount : | ₦4,186,532,350.62 |
Contract Date Signed : | 2019-09-02T10:00 |
Contract Item Classification Scheme : | UNSPSC |
Contract Item Classification ID : | 112893 |
Contract Item Quantity : | 1 |
Contract Item Unit : | unit |
Contract Item Delivery Address : | Abakaliki Ebonyi State |
Implementation |
|
---|---|
Contract Implementation ID: | Kf8GMBiR003389 |
Payer Name : | MINISTRY OF PROJECT MONITORING AND EVALUATION |
Payee Name: | Klyn Construction Ltd |
Contract Period Start Date : | 2019-09-02T07:43 |
Contract Period End Date: | 2020-09-02T22:00 |
Contract Period Duration in Days : | 367 |
Amount Paid : | ₦4,186,532,350 |
Balance to be paid : | ₦1 |
Implementation Status: | complete |