Planning |
|
|---|---|
| OCID: | ocds-zinqhl-U7HKtNBF |
| Project Title: | Re-construction of Ntezi Agba Isu Road (15km) |
| Procuring Entity: | MINISTRY OF WORKS AND TRANSPORT |
| Planning Rationale: | selective tendering |
| Budget ID: | U7HKtNBF003554 |
| Budget Description: | Re-construction of Ntezi Agba Isu Road (15km) |
| Budget Amount: | ₦1,000,000,000 |
| Budget Year: | 2019 Budgetary provision |
| Procurement Method: | selective |
| Procurement Category: | works |
| S/N | Company | Envelope | Bid Opening Status | Tender Amount | Financial Bid Score % | E.O Award Status |
|---|---|---|---|---|---|---|
| 1 | CHINA ZHONGHAO NIGERIA LIMITED | Price BOQ | Opened | 2006787517.09 | 0 | Awarded |
AWARD |
|
|---|---|
| Award Title: | Re-construction of Ntezi Agba Isu Road (15km) |
| Award Description : | Re-construction of Ntezi Agba Isu Road (15km) |
| Award ID : | U7HKtNBFi/U7HKtNBF003557 |
| Award Status : | active |
| Award Date: | 2019-09-23T13:00 |
| Award Criteria : | price Only |
| Award Amount : | ₦2,006,787,517.09 |
| Award Items Classification Scheme : | UNSPSC |
| Award Items Classification ID : | 165157 |
| Award Items Quantity: | 15 |
| Award Items Unit : | kilometer |
| Award Items Delivery Address : | Onicha LGA |
| Contract Period Start Date : | 2019-09-23T13:00 |
| Contract Period End Date : | 2020-09-23T13:00 |
| Contract Period Duration in Days : | 366 |
| Contractor/Supplier Name : | CHINA ZHONGHAO NIGERIA LIMITED |
| Contractor/Supplier Address : | Plot 7 Inwa Abdulkadir Rd Kaduna |
| Contractor/Supplier Email : | chinazhonghao@gmail.com |
| Contractor/Supplier Phone : | 08086838976 |
| Contractor/Supplier website : | https://ebonyieprocure.eb.gov.ng/report/economic_operator.php |
| Procuring Entity Name: | MINISTRY OF WORKS AND TRANSPORT |
| Procuring Entity Address : | ABAKALIKI, EBONYI STATE |
| Procuring Entity Representative Email.: | works@ebonyieprocure.eb.gov.ng |
| Procuring Entity Representative Phone : | |
| Procuring Entity website : | http://www.mowt.eb.gov.ng/ |
Contract |
|
|---|---|
| Contract Title : | Re-construction of Ntezi Agba Isu Road (15km) |
| Contract Description: | Re-construction of Ntezi Agba Isu Road (15km) |
| Contract Award ID : | U7HKtNBF |
| Contract Status : | active |
| Contract Period Start Date : | 2019-09-23T13:00 |
| Contract Period End Date : | 2020-09-23T13:00 |
| Contract Period Duration in Days : | 366 |
| Contract Amount : | ₦2,006,787,517.09 |
| Contract Date Signed : | 2019-09-23T13:00 |
| Contract Item Classification Scheme : | UNSPSC |
| Contract Item Classification ID : | 165157 |
| Contract Item Quantity : | 15 |
| Contract Item Unit : | kilometer |
| Contract Item Delivery Address : | Onicha LGA |
Implementation |
|
|---|---|
| Contract Implementation ID: | U7HKtNBF003559 |
| Payer Name : | MINISTRY OF WORKS AND TRANSPORT |
| Payee Name: | CHINA ZHONGHAO NIGERIA LIMITED |
| Contract Period Start Date : | 2019-09-23T13:00 |
| Contract Period End Date: | 2020-09-23T13:00 |
| Contract Period Duration in Days : | 366 |
| Amount Paid : | ₦2,006,787,517 |
| Balance to be paid : | ₦0 |