Planning |
|
---|---|
OCID: | ocds-zinqhl-004066-EB/WTR/EP002 |
Project Title: | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium (5.8km) |
Procuring Entity: | MINISTRY OF WORKS AND TRANSPORT |
Planning Rationale: | selective tendering |
Budget ID: | 004065 |
Budget Description: | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium (5.8km) |
Budget Amount: | ₦1,704,757 |
Budget Year: | 2018 |
Procurement Method: | selective |
Procurement Category: | works |
S/N | Company | Envelope | Bid Opening Status | Tender Amount | Financial Bid Score % | E.O Award Status |
---|---|---|---|---|---|---|
1 | CHINA ZHONGHAO NIGERIA LIMITED | Price BOQ | Opened | 909010756.5 | 0 | Awarded |
AWARD |
|
---|---|
Award Title: | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium (5.8km) |
Award Description : | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium |
Award ID : | ocds-zinqhl-004066-EB/WTR/EP002i/ocds-zinqhl-004066-E |
Award Status : | active |
Award Date: | 2018-10-15T13:00 |
Award Criteria : | price Only |
Award Amount : | ₦909,010,756.50 |
Award Items Classification Scheme : | UNSPSC |
Award Items Classification ID : | 165157 |
Award Items Quantity: | 5 |
Award Items Unit : | kilometers |
Award Items Delivery Address : | Ikwo L.G.A. |
Contract Period Start Date : | 2018-10-15T13:00 |
Contract Period End Date : | 2019-10-15T13:00 |
Contract Period Duration in Days : | 365 |
Contractor/Supplier Name : | CHINA ZHONGHAO NIGERIA LIMITED |
Contractor/Supplier Address : | Plot No 7, Inuwa Abdulkadi Road Kaduna South, Kaduna |
Contractor/Supplier Email : | NA |
Contractor/Supplier Phone : | 07088459714 |
Contractor/Supplier website : | https://ebonyieprocure.eb.gov.ng/report/economic_operator.php |
Procuring Entity Name: | MINISTRY OF WORKS AND TRANSPORT |
Procuring Entity Address : | ABAKALIKI, EBONYI STATE |
Procuring Entity Representative Email.: | works@ebonyieprocure.eb.gov.ng |
Procuring Entity Representative Phone : | |
Procuring Entity website : | http://www.mowt.eb.gov.ng/ |
Contract |
|
---|---|
Contract Title : | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium (5.8km) |
Contract Description: | Construction of Onu-Igboji Junction to Nwa-Noyo Stadium |
Contract Award ID : | ocds-zinqhl-004066-EB/WTR/EP002 |
Contract Status : | active |
Contract Period Start Date : | 2018-10-15T13:00 |
Contract Period End Date : | 2019-10-15T13:00 |
Contract Period Duration in Days : | 365 |
Contract Amount : | ₦909,010,756.50 |
Contract Date Signed : | 2018-10-15T13:00 |
Contract Item Classification Scheme : | UNSPSC |
Contract Item Classification ID : | 165157 |
Contract Item Quantity : | 5 |
Contract Item Unit : | kilometers |
Contract Item Delivery Address : | Ikwo L.G.A. |
Implementation |
|
---|---|
Contract Implementation ID: | ocds-zinqhl-004066-EB/WTR/EP002004071 |
Payer Name : | MINISTRY OF WORKS AND TRANSPORT |
Payee Name: | CHINA ZHONGHAO NIGERIA LIMITED |
Contract Period Start Date : | 2018-10-15T13:00 |
Contract Period End Date: | 2019-10-15T13:00 |
Contract Period Duration in Days : | 365 |
Amount Paid : | ₦909,010,757 |
Balance to be paid : | ₦0 |
Implementation Status: | Completed |