ocds-zinqhl-004080-EB/WTR/EP002
Construction of concrete lined drain at Abakaliki Fertilizer Plant


Planning

OCID: ocds-zinqhl-004080-EB/WTR/EP002
Project Title: Construction of concrete lined drain at Abakaliki Fertilizer Plant
Procuring Entity: MINISTRY OF WORKS AND TRANSPORT
Planning Rationale: selective tendering
Budget ID: 004079
Budget Description: Construction of concrete lined drain at Abakaliki Fertilizer Plant
Budget Amount: ₦82,502,876
Budget Year: 2018
Procurement Method: selective
Procurement Category: works

Tendering

Tender Title: Construction of concrete lined drain at Abakaliki Fertilizer Plant
Tender Description : Construction of concrete lined drain at Abakaliki Fertilizer
Tender ID : ocds-zinqhl-004080-EB/WTR/EP002
Tender Status : active
Procurement Method : selective
Procurement Category : works
Procurement Method Rationale : selectivetender is required by EU Rules
Award Criteria : price Only
Award Criteria Details : priceOnly
Tender Submission Method : written
Tender Submission Method Details : submission of hardcopy documents
Procuring Entity : MINISTRY OF WORKS AND TRANSPORT
Procuring Entity ID : EB/WTR/EP002
Date of Advert Publishing : 2018-05-01T10:00
Bid Opening Date : 2018-05-25T14:00
Tender Period Start Date : 2018-05-01T10:00
Tender Period End Date : 2019-07-12T14:00
Tender Period Duration in Days : 437
Tender Enquiry Period Start Date : 2018-07-13T10:00
Tender Enquiry Period End Date : 2019-07-12T14:00
Tender Enquiry Period Duration in Days : 364
Tender Award Start Date : 2019-07-12T14:00
Tender Award End Date : 2019-07-12T14:00
Tender Award Duration in Days : 0
Tender Enquiries/Clarifications :
Tender Notice PDF :
Items Classification Scheme : UNSPSC
Items Classification ID : 72141000
Items Quantity: 1
Items Unit : unit
Items Delivery Address: Abakaliki L.G.A
Number of Tenderers: 3
S/N Company Envelope Bid Opening Status Tender Amount Financial Bid Score % E.O Award Status
1 Nina Davito (Nig) Ltd. Price BOQ Opened 8342920.94 0 Awarded

AWARD

Award Title: Construction of concrete lined drain at Abakaliki Fertilizer Plant
Award Description : Construction of concrete lined drain at Abakaliki Fertilizer
Award ID : ocds-zinqhl-004080-EB/WTR/EP002i/ocds-zinqhl-004080-E
Award Status : active
Award Date: 2019-07-12T14:00
Award Criteria : price Only
Award Amount : ₦8,342,920.94
Award Items Classification Scheme : unspsc
Award Items Classification ID : 165157
Award Items Quantity: 1
Award Items Unit : unit
Award Items Delivery Address : Abakaliki L.G.A
Contract Period Start Date : 2019-07-12T14:00
Contract Period End Date : 2019-07-12T14:00
Contract Period Duration in Days : 0
Contractor/Supplier Name : Nina Davito (Nig) Ltd.
Contractor/Supplier Address : No 1 Uncle Daves Close off Enugu Road
Contractor/Supplier Email :
Contractor/Supplier Phone : 08035056851
Contractor/Supplier website : https://ebonyieprocure.eb.gov.ng/report/economic_operator.php
Procuring Entity Name: MINISTRY OF WORKS AND TRANSPORT
Procuring Entity Address : ABAKALIKI, EBONYI STATE
Procuring Entity Representative Email.: works@ebonyieprocure.eb.gov.ng
Procuring Entity Representative Phone :
Procuring Entity website : http://www.mowt.eb.gov.ng/

Contract

Contract Title : Construction of concrete lined drain at Abakaliki Fertilizer Plant
Contract Description: Construction of concrete lined drain at Abakaliki Fertilizer
Contract Award ID : ocds-zinqhl-004080-EB/WTR/EP002
Contract Status : active
Contract Period Start Date : 2019-07-12T14:00
Contract Period End Date : 2019-07-12T14:00
Contract Period Duration in Days : 0
Contract Amount : ₦8,342,920.94
Contract Date Signed : 2019-07-12T14:00
Contract Item Classification Scheme : UNSPSC
Contract Item Classification ID : 165157
Contract Item Quantity : 1
Contract Item Unit : unit
Contract Item Delivery Address : Abakaliki L.G.A

Implementation

Contract Implementation ID: ocds-zinqhl-004080-EB/WTR/EP002004085
Payer Name : MINISTRY OF WORKS AND TRANSPORT
Payee Name: Nina Davito (Nig) Ltd.
Contract Period Start Date : 2019-07-12T14:00
Contract Period End Date: 2019-07-12T14:00
Contract Period Duration in Days : 0
Amount Paid : ₦8,342,921
Balance to be paid : ₦0
Implementation Status: Completed