ocds-zinqhl-t8pme7iM
Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA


Planning

OCID: ocds-zinqhl-t8pme7iM
Project Title: Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA
Procuring Entity: MINISTRY OF WATER RESOURCESS
Planning Rationale: selective tendering
Budget ID: t8pme7iM003381
Budget Description: Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA
Budget Amount: ₦300,000,000
Budget Year: 2019 Budgetary provision
Procurement Method: selective
Procurement Category: works

Tendering

Tender Title: Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA
Tender Description : Re-award for the completion of the concrete works of the Ubu
Tender ID : ocds-zinqhl-t8pme7iM
Tender Status : active
Procurement Method : selective
Procurement Category : works
Procurement Method Rationale : selectivetender is required by EU Rules
Award Criteria : price Only
Award Criteria Details : lowestCost
Tender Submission Method : written
Tender Submission Method Details : written
Procuring Entity : MINISTRY OF WATER RESOURCESS
Procuring Entity ID : EB/WRE/EP005
Date of Advert Publishing : 2019-01-08T10:00
Bid Opening Date : 2019-02-22T14:00
Tender Period Start Date : 2019-01-08T10:00
Tender Period End Date : 2019-02-22T13:00
Tender Period Duration in Days : 45
Tender Enquiry Period Start Date : 2019-01-08T10:00
Tender Enquiry Period End Date : 2021-02-22T13:00
Tender Enquiry Period Duration in Days : 776
Tender Award Start Date : 2019-02-22T13:00
Tender Award End Date : 2020-02-24T14:00
Tender Award Duration in Days : 367
Tender Enquiries/Clarifications :
Tender Notice PDF :
Items Classification Scheme : UNSPSC
Items Classification ID : 112893
Items Quantity: 1
Items Unit : unit
Items Delivery Address: Ohaozara LGA
Number of Tenderers: 3
S/N Company Envelope Bid Opening Status Tender Amount Financial Bid Score % E.O Award Status
1 Elizar Construction Company Ltd Price BOQ Opened 59901150 0 Awarded

AWARD

Award Title: Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA
Award Description : Re-award for the completion of the concrete works of the Ubu
Award ID : t8pme7iMi/t8pme7iM003384
Award Status : active
Award Date: 2019-02-22T13:00
Award Criteria : price Only
Award Amount : ₦59,901,150.00
Award Items Classification Scheme : UNSPSC
Award Items Classification ID : 112893
Award Items Quantity: 1
Award Items Unit : unit
Award Items Delivery Address : Ohaozara LGA
Contract Period Start Date : 2019-02-22T13:00
Contract Period End Date : 2020-02-24T14:00
Contract Period Duration in Days : 367
Contractor/Supplier Name : Elizar Construction Company Ltd
Contractor/Supplier Address : NO. 2 Nnorom St. Abakaliki
Contractor/Supplier Email : elizar@gmail.com
Contractor/Supplier Phone :
Contractor/Supplier website : https://ebonyieprocure.eb.gov.ng/report/economic_operator.php
Procuring Entity Name: MINISTRY OF WATER RESOURCESS
Procuring Entity Address : ABAKALIKI, EBONYI STATE
Procuring Entity Representative Email.: water@ebonyieprocure.eb.gov.ng
Procuring Entity Representative Phone :
Procuring Entity website : http://www.ebonyistate.gov.ng/Ministry/Water/

Contract

Contract Title : Re-award for the completion of the concrete works of the Uburu water project Low Lift Pump Station in Ohaozara LGA
Contract Description: Re-award for the completion of the concrete works of the Ubu
Contract Award ID : t8pme7iM
Contract Status : active
Contract Period Start Date : 2019-02-22T13:00
Contract Period End Date : 2020-02-24T14:00
Contract Period Duration in Days : 367
Contract Amount : ₦59,901,150.00
Contract Date Signed : 2019-02-25T14:00
Contract Item Classification Scheme : UNSPSC
Contract Item Classification ID : 112893
Contract Item Quantity : 1
Contract Item Unit : unit
Contract Item Delivery Address : Ohaozara LGA

Implementation

Contract Implementation ID: t8pme7iM003386
Payer Name : MINISTRY OF WATER RESOURCESS
Payee Name: Elizar Construction Company Ltd
Contract Period Start Date : 2019-02-22T13:00
Contract Period End Date: 2020-02-24T14:00
Contract Period Duration in Days : 367
Amount Paid : ₦59,901,150
Balance to be paid : ₦0
Implementation Status: