Construction of A Section of Umuoghara-Achiegu Road (1.6km)
CONTRACT AWARD PUBLICATION DETAIL
Tender No ocds-zinqhl-003908-EB/WTR/EP002
Advertising/Procuring Entity MINISTRY OF WORKS AND TRANSPORT
Tender Name Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Opening Date 2018-09-03T10:00
Deadline 2018-10-03T13:00
TENDER BIDDERS
S/N Company Envelope Bid Opening Status Tender Amount Financial Bid Score % E.O Award Status
1 Crystal Global Resources Ltd Price BOQ Opened 209318213.97 0 Awarded
DETAILS OF THE PROCUREMENT PROCESS THAT LED TO THE AWARD OF THE CONTRACT
ADVERTISEMENT DETAILS
Tender No
Procurement Plan Name
Advertising/Procuring Entity MINISTRY OF WORKS AND TRANSPORT
Tender Name
Tender Information
Procurement Type Procurement Method
Procurement Method Rationale Procurement Plan Reference Number
Joint Venture Bid Validity Period
Brief Description Tender Fee Payment Not Required
Bid Submission Deadline Date & Time
Opening Date Opening Place
How to Obtain Tender Document
Tender Fee Amount(N:K) ₦0 Procurement Category Invitation to Pre-qualify
Tender Security Bid Security Type
Post Qualification
Local preference Margin of Preference
Bid Security Amount (N:K) Site Visit Date & Time
Bid Security Amount Type Award Criteria Details
Submission Method Details Budget Threshold
Number of Stages Evaluation Mechanism
Framework Agreement Establishment UNSPSC Code
Contracts Awarded in Lots no Number of Lots 0
Number of Lots Allowed Per E.O Lot Number
End of Clarification Period (Date & Time) Date & Time of Advert Publication 2018-09-03T10:00
Funding
Special Characteristics
Place of Delivery

PROCUREMENT METHOD :


Required Bidding document
File Description File Type
Product and materials specifications pdf
bidding document pdf

Planning

OCID:
Project Title: Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Procuring Entity: MINISTRY OF WORKS AND TRANSPORT
Planning Rationale: selective tendering
Budget ID: 003907
Budget Description: Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Budget Amount: ₦1,928,293,489
Budget Year: 2018
Procurement Method: selective
Procurement Category: works

Tendering

Tender Title: Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Tender Description : Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Tender ID :
Tender Status : active
Procurement Method : selective
Procurement Category : works
Procurement Method Rationale : selectivetender is required by EU Rules
Award Criteria : price Only
Award Criteria Details : priceOnly
Tender Submission Method : written
Tender Submission Method Details : written submission
Procuring Entity : MINISTRY OF WORKS AND TRANSPORT
Procuring Entity ID : EB/WTR/EP002
Date of Advert Publishing : 2018-09-03T10:00
Bid Opening Date : 2018-10-02T13:00
Tender Period Start Date : 2018-09-03T10:00
Tender Period End Date : 2018-10-03T13:00
Tender Period Duration in Days : 30
Tender Enquiry Period Start Date : 2018-09-03T10:00
Tender Enquiry Period End Date : 2018-10-03T13:00
Tender Enquiry Period Duration in Days : 30
Tender Award Start Date : 2018-11-09T13:00
Tender Award End Date : 2019-11-08T13:00
Tender Award Duration in Days : 364
Tender Enquiries/Clarifications :
Tender Notice PDF :
Items Classification Scheme : UNSPSC
Items Classification ID : 72141000
Items Quantity: 1.6
Items Unit : kilometers
Items Delivery Address: Ezza North L.G.A
Number of Tenderers: 3

AWARD

Award Title: Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Award Description : Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Award ID : i/ocds-zinqhl-003908-E
Award Status : active
Award Date: 2018-11-09T13:00
Award Criteria : price Only
Award Amount : ₦209,318,214
Award Items Classification Scheme : UNSPSC
Award Items Classification ID : 165157
Award Items Quantity: 1.6
Award Items Unit : kilometers
Award Items Delivery Address : Ezza North L.G.A
Contract Period Start Date : 2018-10-03T13:00
Contract Period End Date : 2019-11-08T13:00
Contract Period Duration in Days : 401
Contractor/Supplier Name : Crystal Global Resources Ltd
Contractor/Supplier Address : Plot 44 Georgelyn drive, phase 2 Ngozika Housing
Contractor/Supplier Email : crystalglobalresources@yahoo.com
Contractor/Supplier Phone : NA
Contractor/Supplier website : https://ebonyieprocure.eb.gov.ng/report/economic_operator.php
Procuring Entity Name: MINISTRY OF WORKS AND TRANSPORT
Procuring Entity Address : ABAKALIKI, EBONYI STATE
Procuring Entity Representative Email.: works@ebonyieprocure.eb.gov.ng
Procuring Entity Representative Phone :
Procuring Entity website : http://www.mowt.eb.gov.ng/

Contract

Contract Title : Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Contract Description: Construction of A Section of Umuoghara-Achiegu Road (1.6km)
Contract Award ID :
Contract Status : active
Contract Period Start Date : 2018-10-03T13:00
Contract Period End Date : 2019-11-08T13:00
Contract Period Duration in Days : 401
Contract Amount : 209318213.97
Contract Date Signed : 2018-10-03T13:00
Contract Item Classification Scheme : UNSPSC
Contract Item Classification ID : 165157
Contract Item Quantity : 1.6
Contract Item Unit : kilometers
Contract Item Delivery Address : Ezza North L.G.A